Current Road & Bridge Improvements

see what we are improving

Current Improvements

See what we are currently working on

The Geauga County Engineer’s Office is responsible for the maintenance of 235 miles of County roads, including improvements to these roads. Below you will find a map showing all county road projects for the current year.

View 2022 Project Map

 

8-4-2021: Washington Street/Haskins Road Traffic Signal begins.  Duration: 150 Days.  Contractor: Terrace Construction.  Project delayed due to supply issues.

3-7-2022: Stafford Road Reconstruction (Messenger Rd to S.R.44) begins. Duration: 60: Days Contractor: Eclipse Co., LLC  

3-28-2022: Bundysburg Road Bridge Replacement & Intersection Re-alignment (at Swine Creek Rd). Road closed & detours posted.  Duration: 180 days. Contractor: Marucci & Gaffney Excavating Co. 

4-20-2022: Thompson Road Resurfacing: Duration: 21 Days  Contractor: Ronyak Paving, Inc

4-25-2022: Aquilla and Butternut Roads Resurfacing.  Duration: 28 Days  Contractor: Ronyak Paving, Inc.

5-16-2022: Bass Lake Road Resurfacing (Newbury Township) : Duration: 21 Days   Contractor: Ronyak Paving, Inc