The Geauga County Engineer’s Office is responsible for the maintenance of 235 miles of County roads, including improvements to these roads. Below you will find a map showing all county road projects for the current year.
View 2022 Project Map
8-4-2021: Washington Street/Haskins Road Traffic Signal begins. Duration: 150 Days. Contractor: Terrace Construction. Project delayed due to supply issues.
3-7-2022: Stafford Road Reconstruction (Messenger Rd to S.R.44) begins. Duration: 60: Days Contractor: Eclipse Co., LLC
3-28-2022: Bundysburg Road Bridge Replacement & Intersection Re-alignment (at Swine Creek Rd). Road closed & detours posted. Duration: 180 days. Contractor: Marucci & Gaffney Excavating Co.
4-20-2022: Thompson Road Resurfacing: Duration: 21 Days Contractor: Ronyak Paving, Inc
4-25-2022: Aquilla and Butternut Roads Resurfacing. Duration: 28 Days Contractor: Ronyak Paving, Inc.
5-16-2022: Bass Lake Road Resurfacing (Newbury Township) : Duration: 21 Days Contractor: Ronyak Paving, Inc